Land Planning Status Classifier
Land planning status: how lenders typically treat each stage
Select the planning status that best describes the land to see how lenders typically approach it
No planning permission
Unconsented land — no current permission for development beyond existing use
Pre-application stage
Formal or informal pre-application discussions with the planning authority underway
Outline planning permission
Principle of development established; reserved matters still to be determined
Full planning permission
Detailed consent granted for a specific scheme
Conditional full permission — complex conditions
Full consent with significant pre-commencement conditions or infrastructure obligations
No planning permission: how lenders typically approach unconsented land
Higher risk — more conservative. Lenders anchor value to existing use and apply conservative leverage. Credible planning rationale and a resilient fallback exit are both important.
- Valuation basis
- Existing use value plus limited hope value where the planning case is credible
- Typical LTV comfort
- Lower than consented sites; often requires a meaningful equity contribution
- Evidence priority
- Planning rationale, professional input, pre-application engagement, constraint assessment
- Exit requirement
- Resilient exit that does not depend solely on planning being granted within a tight window
Key considerations: Planning consultant involvement strengthens the credibility of the planning thesis considerably. Pre-application engagement with the local planning authority is among the most useful evidence. A fallback exit at existing use value materially improves fundability. The bridging term needs realistic buffer for a planning process that takes longer than expected. Access and services should be confirmed independently — planning does not resolve these.
Watch for: Avoid acquiring at a price that reflects development potential on the assumption that bridging at that value will be available. Obtain a planning consultant’s assessment and a preliminary existing use valuation before agreeing the purchase price.
Pre-application stage: how lenders typically approach land at pre-application
Higher risk — improving position. Evidence of engagement with the planning authority adds credibility to the planning thesis, but does not change the unconsented risk profile materially. Valuation remains anchored to existing use.
- Valuation basis
- Still primarily existing use value — pre-application does not create consented land value
- Typical LTV comfort
- Similar to unconsented — conservative leverage applies until consent is granted
- Evidence priority
- Pre-application response, planning consultant advice, constraint assessments, planning thesis
- Exit requirement
- Resilient exit with fallback; timeline must allow for full planning process including any delays
Key considerations: A positive pre-application response from the planning authority is meaningful supporting evidence. Professional planning reports and technical assessments demonstrate that the case has been properly prepared. The planning timeline should be built around the authority’s actual performance, not target timescales. Abnormal costs and constraints identified at this stage should be factored into exit viability modelling. Access and services feasibility should be confirmed alongside the planning work.
Watch for: Pre-application engagement is a strong credibility signal but the risk profile remains close to unconsented until a decision is issued. The term needs to accommodate the full determination period plus buffer, not just the pre-application phase.
Outline planning permission: how lenders typically approach outline consent
Consented — deliverability focus. The principle of development is established, which expands valuation and exit options. Lenders focus on reserved matters status, conditions, obligations, and the timeline to development commencement.
- Valuation basis
- Comparable consented land sales, adjusted for reserved matters status and constraints
- Typical LTV comfort
- More supportive than unconsented; depends on reserved matters status and abnormal costs
- Evidence priority
- Decision notice, conditions, Section 106 obligations, reserved matters status, access and services
- Exit requirement
- Specific exit — sale to developer, development finance application, or reserved matters submission — with realistic timeline
Key considerations: Reserved matters not yet approved mean the planning process has further stages that add time and potential risk. Section 106 agreements and infrastructure contributions need to be understood and costed before relying on them for exit modelling. The decision notice conditions, particularly pre-commencement conditions, determine the realistic timeline to development start. Access rights and services feasibility are assessed independently — outline consent does not resolve these. Development finance lenders will typically engage once outline consent is in place, but may require reserved matters approval before committing.
Watch for: The gap between outline consent and development commencement can be considerable. Model the exit timeline against the actual reserved matters and condition discharge process, not the theoretical minimum. Lenders will scrutinise this carefully.
Full planning permission: how lenders typically approach full consent
Consented — execution focus. The strongest planning basis for bridging. Lenders focus on condition deliverability, obligations, access, services, and whether the exit timeline is realistic given the remaining steps to development commencement.
- Valuation basis
- Comparable consented land sales adjusted for conditions, abnormal costs, and constraints
- Typical LTV comfort
- Most supportive of the planning stages; depends on condition burden and abnormal costs
- Evidence priority
- Full decision notice, all conditions, Section 106, access rights, services feasibility, exit evidence
- Exit requirement
- Specific, evidenced exit — sale comparables, development finance engagement, or defined development programme
Key considerations: Pre-commencement conditions still need to be discharged before development can start — confirm the timeline for each. Section 106 obligations, affordable housing requirements, and infrastructure contributions affect viability and net land value. Abnormal costs including highways works, drainage attenuation, remediation, and services connections should be assessed and factored into residual value. Access rights must be legally established — planning consent does not create or resolve access rights. Development finance lenders typically engage most readily with full consent in place, particularly where conditions are manageable.
Watch for: Full consent is not a guarantee of simple bridging. A consent with heavy conditions, expensive obligations, or unresolved access can still produce a challenging security position. Work through the specific conditions and costs before assuming the exit is straightforward.
Conditional full permission with complex conditions: how lenders approach this position
Consented — condition risk present. Consent is in place but significant conditions or infrastructure obligations remain to be resolved. Lenders focus heavily on the condition discharge timeline, the cost and feasibility of obligations, and whether the exit remains viable once these are fully accounted for.
- Valuation basis
- Comparable consented land value reduced to reflect abnormal costs, obligations, and condition discharge risk
- Typical LTV comfort
- Depends significantly on the cost and timeline of conditions and obligations — can be conservative
- Evidence priority
- Detailed condition schedule, Section 106 obligations, highways and infrastructure cost estimates, discharge timeline
- Exit requirement
- Exit must account for conditions and obligations — a sale or development finance exit needs to work at the net residual value, not headline consented land comparables
Key considerations: Pre-commencement conditions that require technical studies, ecological surveys, archaeological investigations, or highways agreements can take months to discharge. Section 106 obligations with affordable housing requirements, education contributions, and phased trigger points can affect net land value significantly. Infrastructure adoption agreements and highways works can involve lengthy legal negotiations with the local highway authority. Development finance lenders may require specific conditions to be discharged before drawdown — confirm their requirements before structuring the bridging exit around them. A specialist planning lawyer should review the full Section 106 and condition schedule before the bridging term and exit plan are agreed.
Watch for: This is the planning stage most likely to produce a gap between the headline “full consent granted” position and the practical reality of what the consent is worth and when development can start. The exit plan must be built around the net residual value after all obligations, not around comparable headline figures that do not account for the specific obligations on this site.
This tool reflects general patterns in how bridging lenders approach land at different planning stages. Individual lender criteria vary considerably and this does not constitute a lender assessment, financial advice, or a guarantee of any particular product being available. The appropriate approach for any specific land transaction should be confirmed with an experienced broker or adviser.
How to use this tool
Select the planning status that best describes the land in question. The tool shows how lenders typically approach that stage, covering valuation basis, leverage comfort, the evidence they are likely to focus on, and what a credible exit looks like from that position. Each status also includes a watch-for note on the most common pitfalls at that stage.
The five statuses run from unconsented land through to full consent with material conditions. If the land sits between two stages, for example where pre-application engagement is advanced but no decision has been issued, select the earlier stage. Lenders assess the position as it currently stands, not where it is expected to be when the application completes.
The five planning stages
No planning permission
Unconsented land is assessed primarily on existing use value, with lenders applying conservative leverage. The planning case matters, but it does not create consented land value until consent is granted. The most useful evidence at this stage is a credible planning rationale, professional planning consultant input, and an exit that does not depend entirely on planning being granted within a fixed window.
Pre-application stage
Pre-application engagement with the planning authority adds credibility to the planning thesis, but the risk profile remains close to unconsented until a decision is issued. Lenders will look at the quality of the pre-application response and whether the case has been professionally prepared, but valuation still anchors to existing use. The bridging term needs to accommodate the full determination period, not just the pre-application phase.
Outline planning permission
Outline consent establishes the principle of development and expands both valuation and exit options. Lenders shift focus to reserved matters status, Section 106 obligations, pre-commencement conditions, and the realistic timeline to development commencement. The gap between outline consent and development start can be significant, and the exit plan needs to be modelled against the actual process rather than the theoretical minimum.
Full planning permission
Full consent is the strongest planning basis for bridging and typically attracts the most supportive leverage of the five stages. Lender focus moves to condition deliverability, infrastructure obligations, access rights, and whether the exit timeline works once all conditions are factored in. A consent with manageable conditions and a specific, evidenced exit is a straightforward starting point for a bridging application.
Conditional full permission with complex conditions
This category addresses cases where full consent is in place but significant pre-commencement conditions or Section 106 obligations remain to be resolved. These cases can produce a material gap between the headline consented land position and the practical net residual value. Exit modelling must account for the cost and timeline of all obligations — including affordable housing contributions, highways agreements, and infrastructure works — not just comparable headline consented land values.
Squaring Up
Planning status is one of the most significant variables in any land bridging case, and understanding how lenders interpret each stage is useful both before a purchase is agreed and before a case is packaged for submission. The most common difficulty at each stage is not the planning status itself but the exit plan being built around an optimistic reading of it. If you are considering bridging finance for a land acquisition, the Bridging Timeline Readiness Checklist and the Bridging Exit Strategy Checklist are useful companions. For a broader overview of bridging finance, visit our bridging loans hub.
Disclaimer: This page is for information only and does not constitute financial advice. Figures, rates, and examples are illustrative. Your circumstances will affect what products and terms are available to you. Always speak to a qualified adviser before making financial decisions.